Skip to main content

Find Books, Movies, Music and More

logo that says Questions? Click to Chat online with a Librarian

Featured Database

eMediaLibrary logo
Glen Ellyn Library cardholders may download audiobooks and ebooks to supported devices with eMediaLibrary.

Macy's

Glen Ellyn Chamber of Commerce logo

You are hereLibrary Building Repairs Fact Sheet

Library Building Repairs Fact Sheet


Key Purpose
The key purpose of the proposed bond issuance is to repair deficiencies in the roof, water infiltration in exterior walls and windows, improper ventilation of the roof, and outdated software that operate the mechanical systems that maintain a comfortable library environment. The main purpose of the operating rate increase is to create a capital replacement and repair budget line that will allow ongoing capital improvements and repairs to be made to the building.
photograph showing metal studs rusting due to leakage
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Background
In 1993, voters approved the sale of bonds for the construction of the current library building. Construction of the current building began in 1994 and the building opened for operation in 1995. The building came in under budget. However, neither the proceeds of the bonds nor the library’s annual budget provided for either expected or unexpected repairs, maintenance, or replacement of building components, systems and equipment. The building is now fourteen years old and in need of mechanical and physical repairs. The library is governed by a board of seven elected trustees, who over the last several years have become increasingly aware of the need for these repairs and the absence of any funding for them.

photograh showing interior drywall damage 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
The board first addressed building problems in 2002 and 2005 by hiring two roofing experts because the roof had leaked periodically for some time. The second expert found deficiencies in the roof, and his investigation ultimately led to the discovery of other problems, including water infiltration in exterior walls and windows, improper ventilation of the roof, and outdated software that operate the mechanical systems that maintain an appropriate library environment. The board has concluded that these deficiencies are allowing further damage to occur to the building. The board feels strongly that these deficiencies, if not addressed promptly, will cost all of us a lot more in the future than it would cost to borrow sufficient funds to correct the known problems now.

photograph showing Deterioration of wood framing
 
 
 
 
 
 
 
 
 
 
 
 
 
Project Scope
The proposed project work will include partial removal and replacement of exterior wall cladding, remediation of mold, removal and reinstallation of windows, roof replacement with installation of proper ventilation, masonry repairs, sealing the building envelope, mechanical system upgrades and parking lot repair.

Impact to Library Users
We anticipate this project can be completed with minimal interruption to library patrons, staff and neighbors. If the rate increase and bond issuance occur in early 2010 work is expected to begin in Spring 2010.

Estimated Project Cost
The Library hired a series of building and environmental consultants to investigate the water, mold, heating, cooling and building envelope issues and provide recommendations on resolving the situation in the most cost –effective and environmentally safe manner. The board estimates the cost of the repairs will be $3,000,000.

Cost to Taxpayers
In the past, the board has not budgeted for ongoing maintenance, repair, or capital replacement. To rectify this situation, and to provide the funds necessary for immediate repairs, the board proposes a two part solution. The board proposes to borrow 3 million dollars to fund urgently needed repairs. It expects to be able to borrow that amount at an average rate of approximately 3.5% per year, payable over 11 years. In addition the board proposes to increase our tax levy for the operation of the library by 3 cents from .1649 to .1949, which is within the amount approved by the voters in 1977. This increase in operating rate will be used to fund ongoing maintenance, repairs, and capital replacements. For a home with a market value of $300,000 the impact of these two proposals would add approximately $35 to the annual property tax bill.

photograph showing buckled sheet metal and curling shingles
 
 
 
 
 
 
 
 
 
 
 
 
 

More Info Available

An additional set of FAQ’s are available at the library or on the website at www.gepl.org.

Attend an Informational Meeting on October 5, 2009 at 2pm, October 6, 2009 at 7pm and October 10, 2009 at 2pm in the meeting room on the 1st floor of the library, 400 Duane Street, Glen Ellyn, IL 60137.

E-mail or phone Library Director,
Dawn Bussey at dbussey@gepl.org
or 630-790-6760 or contact Lawrence A. Stein, Library Board President, at lstein@gepl.org.

Back to Library Building Repairs and Maintenance